Matina Enclaves construction  updates: Bldg B 96%, Bldg C 30%

Bldg C East View
Bldg C East View

Escandor Development Corporation recently released its latest construction updates for the two ongoing condominium building construction work of its maiden venture Matina Enclaves.

Building B is now at 96 percent and is on track for a turnover tentatively set next month.

The latest update was released based on May 15 report.

The elevator is now fully functional while completion is being done on the Lobby and Atrium (Common Area). Units are likewise undergoing finishing prior to turnover.

The second condominium, Building C, has now an overall accomplishment of 30 percent. At the moment, the concreting of the fourth level is underway while the two-level parking and first residential floor is is already complete.

Four other fully sold condominium buildings of the signature project of homegrown developer Escandor Development Corporation (Esdevco) are set for construction.

Homebuyers of the sprawling complex will be waking up with the majestic view of the picturesque Mt. Apo virtually framed on their windows.

Matina Enclaves, built with an environment-friendly mindset, is a virtual patch of nature where a community thrives amidst a metropolitan setting.

A few steps away is the Davao City Golf Club, a vast ground of lush greenery for one enamoured with the sport.

Around the complex are pathways dotted with trees where one can walk, jog or bike. The amenities too are family-oriented–a clubhouse with recreational facilities for both the young and old, lap pool, and soon, the Arcadia which is a modern gaming complex right across the road.

To top it, Matina Enclaves is a gated complex which only means that exclusivity is mixed with leisurely condo living.

SHARE