Esdevco releases latest Matina Enclaves construction updates 

Escandor Development Corporation (Esdevco) recently released the construstion updates for its maiden project Matina Enclaves.

Project head Gerard Kent Garces on June 8 bared the contractor’s report for the completion rate for Building B which was placed at 96.5 percent while Building C is at 35 percent.

“We are satisfied with the progress of the construction works and so far we are right on target,” Garces said.

Building B is set for turnover late this month although there is no final announcement yet from the developer.

Building B now has a fully functional elevator while the Lobby is undergoing ongoing Atrium architectural work. It serves as the common area of the building.

Also ongoing is the construction of the Pool Deck and minimal unit finishes.

For Building C, construction on ongoing on the concreting of the 4th level. Likewise, the solid block is being installed along with the precast. The second floor parking is already complete.

Matina Enclaves, located at Quimpo Boulevard along Ecoland, Davao City, is a sprawling gated residential complex. It is the maiden venture into real estate development of the homegrown Esdevco owned by the Escandor family.