Department of Public Works and Highways Unified Project Management Office (DPWH UPMO) Roads Management Cluster I Engineer Divina Bulan shared the progress of the construction of the Davao City Bypass Construction Project (DCBCP).
Bulan told Edge Davao that they are now in the construction of a 4 lane-45.62 km highway (2 lanes each direction), including two 2.3 km mountain tunnels, two Cut and Cover Tunnel (315 m and 130m) at Cabantian Intersection and a 600-meter underpass along Davao- Bukidnon Road Intersection.
Bulan reported that for Package 1-1, which includes a 2.30-kilometer New Austrian Tunneling Method (NATM) tunnel, the civil works is ongoing and is 52.721 percent complete; Package 1-2 is the contract agreement for concurrence of the Japan International Cooperation Agency (JICA); Package 1-3 with civil works ongoing is at 1.792 percent complete; Package II-1 with civil works also on-going at 53.02 percent complete; Package II-2 with civil works also on-going at 38.619 percent complete; and Package 11-3, which is the procurement will be undertaken by fourth quarter of 2024.
The DCBCP is a 45.5-kilometer bypass road that runs from Barangay Sirawan in Toril, Davao City to Barangay J.P. Laurel in Panabo City.
Upon completion, the bypass road will cut the one-hour-and-44-minute-long land travel via Maharlika Highway to only 49 minutes.
The construction of the DCBCP started in December 2020 and is expected to be completed in December 2027.