Transportation Secretary Jaime J. Bautista reiterated on Thursday the need to update the Feasibility Study (FS) of the first phase of the Mindanao Railway Project (MRP) and one of the considerations is to look at the possibility of making it a two-track electric-powered train system.
Bautista added that DoTr is now in the process of procuring a consultant to prepare the feasibility study.
“We need to update the FS of the MRP Phase 1 which will run from Tagum-Davao-Digos (TDD) segment. Yung old study will be operated with a diesel-powered train, seguro its not. Isa sa mga titingnan ng ating consultant ay kung puwede ma-two track. Kagaya ng na mention ko seguro it’s a about time that we operate an electric-powered train,” he said during the 1st Mindanao Infrastructure Summit held at SMX Convention Center in SM Lanang Premier.
In 2018, the proposed two-track electric train system for the main line of the MRP was approved by the DoTr.
Also in 2018, the National Economic and Development Authority (NEDA) approved a single-track diesel-powered Mindanao train.
Meanwhile, another consideration being eyed in the updated FS for the MRP is it should include the potential integration of a freight line to maximize the project’s overall benefits following Bautista’s announcement in February this year that the project is facing a funding challenges after China withdrew its loan deal with the Philippines last year.
He said the government is seeking alternative funders for the MRP through the Department of Finance (DoF).
In June this year, in a letter sent to Secretary Leo Tereso A. Magno, chairman of the Mindanao Development Authority (MinDA), DoTr Undersecretary for Railways Jeremy Regino informed Magno that the acquisition of the right of way (RoW) for the TDD segment of the MRP was progressing in all designated areas, except for Davao City and Panabo City, where funding constraints are hindering progress.
Regino assured that the acquisition of RoW remains a top priority to ensure that construction can commence seamlessly once the project funding source has been resolved.
Regino said that the acquisition of RoW remains a top priority.
“Efforts are underway to identify and secure potential funding sources to finance the completion of the MRP. A multi-faceted approach is being employed, exploring various avenues for funding sources, including government allocations, public-private partnerships, and multilateral funding,” Regino said in his letter.
The TDD segment covers 100 kilometers with eight railway stations and two depots.
With an estimated total cost of approximately P81.7 billion, the project aims to reduce travel time from Tagum City in Davao del Norte to Digos City in Davao del Sur from three hours to an hour, benefiting around 1,222 daily commuters.