Tagum-Davao-Digos segment of MRP project still awaits shortlist of bidders from Chinese gov’t

DOTr Photo

Looks like it will take more time before the trains between the cities of Davao and Tagum in Davao del Norte will start running.

The Department of Transportation (DoTr) is still awaiting the shortlist of bidders for the Design and Build Contractor that will be provided by the Chinese government for the construction of the first phase of the Mindanao Railway Project (MRP).

The Design and Build Contractor will provide official development assistance (ODA) to partly fund the P82.9-billion first phase, which is the Tagum-Davao-Digos (TDD) segment.

“The Mindanao Railway Project ay tuloy. Ito ang isang proyekto that will be pushed through. At present we are just waiting for the shortlist of bidders for the Design and Build Contractor to be provided by the Chinese government. Ang proseso ay magbibigay ng listahan ang China na tatlo at yun ay magkakaroon ng bidding amongst themselves,” said DoTr Secretary Arthur Tugade in a virtual press conference.

Tugade said as soon as DoTr receives the shortlist of bidders, procurement and construction of MRP will follow.

“Pagkatapos ng shortlist na ito ay uusad at uumpisahan na ang procurement at construction at sana ay maumpisahan na bago magtapos ang taon na ito,” he said.

Tugade also said DoTr is in the process of finishing the procurement for the project management consultant and is expecting that the contract will be awarded next month.

“Karagdagan diyan ay tinatapos namin yung procurement ng project management consultant at inaasahan namin na magkakaroon na ng award nito sa dadating na buwan,” he said.

Tugade said geotagging and other activities in line to the right of way (ROW) acquisition are ongoing.

“Ginagawa namin yung geotagging at tinatapos na ang ROW upang mailagay sa tamang ayos at tamang lugar. Ito ay isang proyektong ating itutuloy at we are working on partial operability, hopefully, at the end of the term of President Rodrigo Duterte,” he said.

In an interview with MRP Project Manager Clipton J. Solamo last year, he said partial operation of Mindanao railway is targeted fourth quarter of 2021, and the full operation of the railway’s first phase — covering Tagum, Davao, and Digos City in Davao del Sur — is seen by the second quarter of 2022.